Black Sea Coast Road, Arakli-Iyidere
|
|||
Project Location | Trabzon / TURKEY | ||
Employer | TR General Directorate of Highways (KGM) | ||
The name of the job | Araklı – Iyidere Road Km: 80+220 – 107+135 “Leveling, Engineering Structures, Bridge, Tunnel, Sub-base, Plantmix Foundation and Bituminous Hot Mix etc” Works. | ||
Total Contract Price | 174,659,948.10 USD | ||
Type of Work Done | |||
Total Path Length | 27 km, 2 x 2 Lane | Excavation | 3.725.050 m³ |
Filling | 3.087.000 m³ | Coastal Fortification | 8,356,250 tons |
Earth Retaining Walls | 58,072 m² | Retaining Walls | 5,874 m |
Sub-Base | 438,000 tons | Base Layer | 453,000 tons |
Asphalt Paving | 761,000 tons | Asphalt Wear Layer | 806,000 m² |
Number of Bridges | 26, Length = 3,405 m | Number of Tunnels | 1, Length = 574 m |
Number of Overpasses | 2 | Number of Underpasses | 8, Length = 531 m |
Number of Prefabricated Beams | 1801 | Number of Box and Pipe Grilles | 141, Length = 8.193 m |
Concrete | 185,000 m³ | Pile Works | 21,749 m |