Istanbul Bus Terminal – Bağcılar Rail System Construction and Electro-Mechanical Works

Istanbul Otogar-Bağcılar Rail Public Transportation System Construction, Electro-Mechanical
Works and Vehicle Supply 
Project Location Istanbul Turkey
Employer Istanbul Metropolitan Municipality, General Directorate of IETT
The name of the job Istanbul Bus Terminal-Bağcılar Rail Public Transportation System Construction, Electro-Mechanical
Works and Vehicle Supply
Total Contract Price 1,355,277,095.16 USD
Type of Work Done
Tunnel Length 26.234 m – EPB – CPC Number of Stations 16 ( 5 Stations were built with Diaphragm
Wall and Top-Down Construction Method.)
3,740 m – NATM Earthworks 5.888.513 m³ – Excavation
909 m – 2 Viaducts 2,069,000 m³ – Fill
2.195 m – Open & Close Shoring Works 139,060 m² – Diaphragm Wall
46,000 m – Single Line Length 35.423 m³ – Shotcrete
Tunnel Diameter TBM – 6.50 m 149,058 m – Bored Pile
NATM – 7.80m 700,553 m – Anchor
segment 18,995 Rings (5 Panels + 1 Switch) Concrete 914,788 m³

 

Other Documents