| Konya – Akşehir – Afyon Road
| |||
| Project Location | Konya and Afyon Provinces Within the Boundaries of the 3rd Regional Directorate of Highways | ||
| Employer | TC GENERAL DIRECTORATE OF HIGHWAYS | ||
| The name of the job | Construction of Konya-Akşehir-Afyon Road KM:102+500-123+700 and KM:131+500-157+000 Sections | ||
| Total Contract Price | 102,427,037.21 TRY | ||
| Type of Work Done | |||
| Groundworks, bridges and artworks | |||
| Road construction | 46.7 KM | ||
| Tunnel 3 | 1615 m, diameter: 10.5 m | ||